Mont Blanc | Reorganizing Production and Material Flow Reduces Lead Times

Customer References

Shorter Lead Times in Gold Nib Manufacturing

Mont Blanc | Reorganizing Production and Material Flow Reduces Lead Times

Optimized Material Flow and Leveled Production Scheduling at MONTBLANC

Shorter Lead Times
Lower Work-in-Process Inventory
Heijunka Production Leveling

The Starting Point

Manufacturing gold nibs for MONTBLANC fountain pens is a complex, largely manual process involving up to 35 distinct steps. A wide range of product variants and bottlenecks that shifted daily placed significant demands on production scheduling.

Electronic planning boards had already improved visibility into production scheduling. The next step was to reorganize the entire production setup. The goal was to significantly shorten lead times and reduce work-in-process inventory while improving material flow throughout the gold nib workshop.

 

-Hamburg, Germany

-Luxury Goods / Writing Instruments

-Complex, High-Variety Craft Manufacturing

Reorganizing Material Flow and Production

Departmental structures that had evolved over time and new investments had left material flow poorly aligned with the needs of steady production. At the same time, three production groups had to be reorganized within the existing, relatively cramped facilities.

The project team redesigned the material flow and department layout, divided manufacturing into production segments, and introduced Heijunka leveling into production scheduling. The aim was to smooth out the impact of fluctuations in incoming orders and stabilize capacity utilization.

New Production Structure for the Gold Nib Workshop

Optimized Material Flow in a U-Shaped Layout

The three production groups were arranged in a space-saving U-shaped layout with a central material supply point. Centralized receiving and dispatch points and staging areas shorten travel distances and make it easier to track the flow of materials.

Segmented Production

The former job-shop setup was reorganized into production segments. Continuous flow across these segments helps significantly reduce lead times and work-in-process inventory.

Production Leveling with Heijunka

Heijunka scheduling smooths out the impact of fluctuations in incoming orders and helps keep capacity utilization more consistent. Each production group uses its own Heijunka board to schedule production orders each day based on available capacity.

“Shorter lead times come not just from working faster, but from organizing material flow effectively and leveling the production workload.”

MONTBLANC – Project to Reorganize the Gold Nib Workshop

Lower Work-in-Process Inventory and Significantly Shorter Lead Times

The new production structure consists of four internal and three external segments. Each production order is expected to pass through a segment within one working day. The previous average lead time was 33 working days. The new structure targets a lead time of 10 working days.

Less Work in Process (WIP)
50 %

Significantly Less Material in Process

 

With production organized into segments, the process requires 50–65% less material than was previously held in work-in-process inventory. The new structure also makes it possible to significantly shorten lead times.

The reorganization of the gold nib workshop brought material flow, layout, and production scheduling into alignment. Production segments, an optimized U-shaped layout, and Heijunka leveling create a steadier production flow. Lead times and work-in-process inventory are tracked daily for each production group, segment, and workstation and reviewed regularly.

About MONTBLANC

Montblanc International GmbH manufactures high-end writing instruments, watches, jewelry, and leather goods. The company is headquartered in Hamburg, Germany. The case study reports approximately 3,300 employees worldwide, including around 1,000 in Hamburg.

FAQ – Frequently Asked Questions

How did Montblanc improve material flow in its gold nib workshop?

Montblanc arranged three production groups in a space-saving U-shaped layout. A central material supply point, shared receiving and dispatch points, and designated staging areas shorten travel distances and make material flow easier to track.

Montblanc is targeting an average lead time of 10 working days. Before the reorganization, the average was 33 working days. The new structure includes four internal and three external production segments. Each order is expected to pass through a segment within one working day.

By how much does segmenting production reduce work-in-process inventory at Montblanc?

With the new production structure, Montblanc needs 50 to 65% less work-in-process inventory than before. Within each production segment, the individual steps are arranged for continuous flow. Montblanc records work-in-process inventory and lead times daily to track changes over time.

Montblanc uses Heijunka to keep production workloads steady even as incoming orders fluctuate. Each production group has its own Heijunka board and uses it daily to decide which orders it can start based on available capacity.