Higher Throughput and Better On-Time Delivery
Driescher | New Logistics Business Model and a Value Stream Aligned with Market Demand
Value Creation Aligned with Market Demand and Optimized Production Control with DISKOVER
The Starting Point
Increasing market volatility, a growing range of product variants, and ever shorter delivery lead times posed mounting challenges for DRIESCHER.WEGBERG. Committed delivery dates were fixed. Keeping those commitments required extensive coordination and extra work, disrupting production and final assembly.
Backlogs and long lead times were particularly problematic in component manufacturing. Missing components disrupted final assembly, and meeting some delivery dates depended on high inventory levels, flexible work schedules, and considerable coordination.
-Wegberg, Germany
-Switchgear & Switching Devices
-High Degree of In-House Manufacturing and Wide Product Variety
Aligning Complex Manufacturing with Market Demand
The existing order-based production model struggled to keep pace with a growing range of product variants and shorter delivery deadlines. Ongoing coordination among component manufacturing, the central warehouse, final assembly, and the order center required considerable manual effort.
An analysis also showed that the backlog in component manufacturing averaged 21 working days. The goal was to develop a new logistics business model that would shorten lead times, improve capacity utilization, and support reliable on-time delivery.
Aligning Production with Market Demand Using DISKOVER
80/20 Production Leveling & Push/Pull Control
Standard parts needed regularly are replenished through a pull system, while order-specific components continue to be produced as needed using push scheduling. This allows production capacity to be allocated more effectively.
Kanban for Final Assembly
A Kanban system was introduced for regularly needed items. In total, 3,176 items across eight assembly areas were switched to a two-bin Kanban system. As a result, availability of standard components exceeds 98% in some cases.
Automated Maintenance of Planning Parameters
DISKOVER helps regularly optimize planning parameters, reviews which items are assigned to push or pull control, fine-tunes 80/20 production leveling, and adjusts Kanban inventory levels to match demand.
“Aligning production with market demand combines short lead times and reliable on-time delivery with production control that responds to actual demand.”
DRIESCHER.WEGBERG
Significantly Shorter Lead Times and Better On-Time Delivery
The new approach to production control reduced work-in-process inventory, ensured that production orders were released on time, and established a process for managing day-to-day capacity. Within six months, the average lead time for production orders fell significantly.
Within six months, the average lead time for production orders fell to just four working days. Throughput and on-time delivery improved while production capacity stayed the same.
DRIESCHER’s new logistics business model combines push and pull production control, Kanban, day-to-day capacity management, and systematic optimization of materials planning. DISKOVER helps DRIESCHER regularly review how production is segmented, adjust planning parameters, and size Kanban inventories to match demand. The result is smoother production with short lead times, high availability, and better on-time delivery.
About Fritz Driescher KG
Based in Wegberg, Germany, Fritz Driescher KG is a medium-sized company specializing in the design and manufacture of switchgear and switching devices for power supply systems. Its product range includes medium-voltage switchgear and switches, transformer substations, low-voltage switchgear, and high- and low-voltage fuse links.
- Wegberg, Germany
- Power Engineering / Switchgear Manufacturing
FAQ – Frequently Asked Questions
How did DRIESCHER.WEGBERG shorten production lead times?
Within six months, DRIESCHER.WEGBERG reduced the average lead time for production orders to four working days. The company cut work-in-process inventory and timed the release of production orders to match both demand and available capacity. Throughput and on-time delivery improved while production capacity stayed the same.
How does DRIESCHER.WEGBERG combine push and pull production control?
Under the pull system, standard parts used regularly are replenished when consumption triggers a replenishment signal. Under the push system, order-specific components are scheduled and produced based on individual customer orders. This helps DRIESCHER.WEGBERG allocate production capacity more effectively.
How does two-bin Kanban improve material supply to final assembly?
In a two-bin Kanban system, an empty bin triggers replenishment. The second bin supplies the assembly line until the first bin is refilled. DRIESCHER.WEGBERG switched 3,176 items across eight assembly areas to this system. As a result, availability of standard components exceeded 98% in some cases.
What role does DISKOVER play in production control at DRIESCHER.WEGBERG?
DISKOVER helps DRIESCHER.WEGBERG regularly review and adjust its materials planning parameters. This includes checking which items are best suited to push or pull control and determining how much Kanban stock is needed. This allows the company to adapt its material supply as demand changes.